By June this year, Guangdong's renewable energy installed capacity had surpassed 100 million kilowatts, exceeding coal power for the first time, contributing over 60 percent of new power capacity added since 2020.
This finding was included in a report submitted to the 27th session of the Standing Committee of the 14th Guangdong Provincial People's Congress on Sept 29.
According to the report, Guangdong's total installed power capacity reached about 280 million kW as of June this year, nearly double the level recorded in 2020. The province has led China in nuclear, gas and pumped-storage capacity for several years.
Energy intensity fell by over 17 percent during the 14th Five-Year Plan period (2021-25), and stood at 0.31 metric tons of standard coal per 10,000 yuan ($1,491.4) in 2025, about two-thirds of the national average.
The report also showed that Guangdong Power Grid had connected 92.94 million kW of new energy as of June, accounting for 33.6 percent of total installed capacity, with utilization rates above 99 percent throughout the 14th Five-Year Plan period.
In energy technology, Guangdong has produced notable results, including the Hualong One third-generation nuclear technology and the world's largest monolithic floating wind platform, "Mingyang Tiancheng".
The province's new energy industry cluster surpassed 1 trillion yuan in revenue in 2024, becoming its ninth trillion-yuan industrial cluster, and reached more than 1.18 trillion yuan in 2025, ranking first among the province's 10 strategic emerging industry clusters for three consecutive years.